Works Description
Greymouth CBD Renewal Project consisted of excavation, removal and replacement of the existing road pavement, followed by installation of kerb, channel and footpaths. We conducted extensive ground and pavement preparation works for the installation of interlocking pavers. We enabled water and stormwater renewal and installation works.
Delivery Type
Head Contractor
Completion
November 2017
Contract Value
$1.4 million
Our mission is to deliver innovative earthworks solutions through customer driven staff and technically advanced plant.